Inventory Management Goods Receipt In Sap MM

Ratings:
(4)
Views:0
Banner-Img
  • Share this blog:

Goods Receipt

SAP Goods Receipt Process Flow

  • The company Sends a PO to the Vendor
  • The vendor will send Material to Company based on the PO may be full quantity or partial quantity to the delivery address mentioned in the PO
  • The company makes a Goods Receipt
  • GR will be done at the plant premises called the GR area
  • During the GR, the system will generate one material document as a proof of action i.e. GR and it also generates Accounting

The diagram shows an overview of all the key effects of a goods receipt referencing a purchase order.

At the goods receiving point

  • The system checks whether the delivery is the same as the purchase orders data, that is, whether the goods that were ordered have been delivered.
  • The system suggests data from the purchase order when you enter the receipt of the goods (for example, items and quantities). This makes it easier to enter the receipt of the goods and check over deliveries and under deliveries when goods arrive.
  • The purchase order history is automatically updated as a result of the deliveries.
  • The Purchasing Department can send a reminder about late deliveries.
  • When you post a goods receipt to the warehouse, the system creates a material document containing information such as the material delivered and the quantity delivered. The system also records the storage location in which you place the material into stock in the plant concerned.
  • In transactions relevant to material valuation, the system creates at least one accounting document, which records the effects of the goods movement on the value of the stock.
Inclined to build a profession as SAP MM Developer? Then here is the blog post on, explore SAP MM Training

Result of the goods receipts posting

1. Creation of the Material Document

When you post a GR, the system automatically creates a material document that serves as proof of the good's movement.

2. Creation of the Accounting Document

Parallel to the Material Document, the system creates an accounting document.

3. Creation of goods receipt/issue slip

When you enter GR you can print GR/Issue slip

4. Sending a mail message to Purchasing

If the GR message indicator has been set in PO, the buyer automatically receives a message about the delivery

5. Stock update

Stock will be updated in the material master record, depending on the destination of the goods

6. Good receipt into the warehouse

Here the system will increase the total valuated stock and the stock type (unrestricted etc) by the delivered quantity. The stock value is updated at the same time.

7. Good receipt into the consumption

Only the consumption statistics are updated in the material master record. [However, it does not update this stock for SPL stock like sales orders, project stock]

8. Good Receipt into GR blocked stock

The stock levels remain the same - It records only in the PO history

9. GR into a new storage location

A new storage location will be created when GR is posted (Provided customizing of automatic creation of storage location is done already) - Otherwise, you have to add a new store location to the material master before you post a GR to it.

10. Update the GL accounts

The system automatically updates the G/L accounts by the value of the receipt of the goods.

11. UPdate in PO

PO History:

During the GR a PO history record will be automatically created which contains data like delivered qty, Mat doc no, item, Mat type and posting dates of GR

PO Item:

If the delivery completion indicator is set in the mat document the order is considered to be closed and the open PO qty is set to be zero

12. Other Updates

Depending on the characteristics of the material, movement, and components used other updates are carried out:

  • Entries will be made in the planning file or independent requirements reduction in the mat. Page
  • Statistical data in Inventory controlling
  • Vendor evaluation data in purchasing
  • Transfer requirements and quota in WM
  • Inspection lots in QM
Checkout our Blog on SAP MM Tutorial

Effects of GR on PO and Material Master 

Before GR        After GR In PO   
Header Data    Header   data 
Status view  Status View
Order Qty - X  Order Qty - X
Delivery. Qty - 0  Deli. Qty - Y 
Still to be del - X  Still to be del X - Y 
Item Overview   Item Overview
No New tab called PO history   A new tab PO History create 
Delivery Tab    Del. Completed indicator 

(No check/masked) (If full PO Qty receives)  

In Material master 

No New View                                                                             A new view will be added

For Plant stock                                                                            for plant stock

For Storage loc stock                                                                   for the storage location

You liked the article?

Like : 0

Vote for difficulty

Current difficulty (Avg): Medium

Recommended Courses

1/15

About Author
Authorlogo
Name
TekSlate
Author Bio

TekSlate is the best online training provider in delivering world-class IT skills to individuals and corporates from all parts of the globe. We are proven experts in accumulating every need of an IT skills upgrade aspirant and have delivered excellent services. We aim to bring you all the essentials to learn and master new technologies in the market with our articles, blogs, and videos. Build your career success with us, enhancing most in-demand skills in the market.


Stay Updated


Get stories of change makers and innovators from the startup ecosystem in your inbox